Progress Payments: How to Never Be More Than One Check Behind

By 2GetPaid Team ยท December 2025 ยท 7 min read

50% upfront sounds aggressive until you've lost $18,000 on a job. Progress payments protect you from clients who won't pay until they have all the leverage.

๐Ÿ“‹ Key Takeaways

  • Never work without payment โ€” 25-25-25-25 or 50-25-25
  • Payment before work โ€” not after
  • Tie payments to milestones โ€” demo, rough-in, finish
  • Stop work if payment stops โ€” no exceptions
"I lost $18,000 on a kitchen remodel because I didn't structure the payments right. They paid 30% upfront, then kept asking for changes. By the time I was done, they owed me $18,000 and refused to pay until I fixed things that weren't in the original scope. Never again. Now it's 25-25-25-25, no exceptions."

โ€” Kitchen & bath contractor, Chicago, IL

Here's a scenario every contractor knows:

You're 75% done with a $30,000 bathroom remodel. You've bought materials. You've paid your crew. You've worked three weeks.

And you've received $0.

The client said they'd pay "at the end." Now they're nitpicking every detail, threatening to withhold payment, and you have zero leverage because they already have all the work.

This is how contractors go out of business.

The Rule: Never More Than One Payment Behind

Here's the golden rule of contractor payments:

At any point in the project, the amount of work completed should not exceed the amount paid by more than one milestone.

This means if you're doing a $30,000 job with four payments of $7,500 each:

At no point are you more than one payment ($7,500) behind.

If the client stops paying, you stop working. You're out one payment, not the whole job.

What Are Progress Payments?

Progress payments (also called milestone payments or draw schedule) break a large project into smaller, scheduled payments tied to specific points in the project.

Instead of:

You do:

Each payment is tied to a milestone. When the milestone is complete, payment is due.

How to Structure Progress Payments

Typical 4-Payment Schedule

Payment 1 โ€” Deposit (25%): Due before work begins. Covers initial materials and mobilization.

Payment 2 โ€” Rough-In (25%): Due when rough-in is complete. Electrical, plumbing, framing done.

Payment 3 โ€” Pre-Finish (25%): Due before finish work begins. Drywall, flooring, prep work done.

Payment 4 โ€” Completion (25%): Due at substantial completion. Before punch list is finished.

Typical 3-Payment Schedule (Smaller Projects)

Payment 1 โ€” Deposit (33%): Due before work begins.

Payment 2 โ€” Mid-Point (33%): Due at halfway point or significant milestone.

Payment 3 โ€” Completion (34%): Due at substantial completion.

Material-Heavy Projects

If materials are a significant portion of the cost, structure payments differently:

Payment 1 โ€” Materials (100% of materials): Due before ordering. Materials become client property.

Payment 2 โ€” Deposit (25% of labor): Due before work begins.

Payment 3 โ€” Rough-In (25% of labor): Due at rough-in.

Payment 4 โ€” Completion (50% of labor): Due at completion.

This way, you're never fronting material costs.

Defining Milestones

Milestones need to be specific and verifiable. Vague milestones lead to disputes.

Bad Milestones

Good Milestones

Tip: Use inspection milestones when possible. "After rough-in inspection passes" is objective. "After rough-in is done" is subjective.

What "Substantial Completion" Means

The final payment is typically due at substantial completion โ€” not when everything is perfect.

Substantial completion means:

Define this in your contract:

"Substantial completion" means all work described in the Scope of Work is installed and functional, excluding minor punch list items such as touch-up paint, minor adjustments, and cosmetic items. Final payment is due upon substantial completion, not completion of punch list.

This prevents clients from withholding final payment over minor punch list items.

How to Present Progress Payments to Clients

Some clients push back on progress payments. Here's how to frame it:

1. It's Standard Industry Practice

"Progress payments are how every professional contractor works. It protects both of us by ensuring I have the resources to complete your project on time."

2. It Ensures Quality

"By breaking the project into phases, I can focus on each phase without worrying about cash flow. This ensures your project gets the attention it deserves."

3. It Protects the Client Too

"If I don't complete a milestone, you don't pay for the next one. This gives you leverage throughout the project, not just at the end."

4. It Matches Costs

"Payments are structured to match when I incur costs โ€” materials at the beginning, labor throughout. This is how professional contracting works."

What If the Client Wants to Pay at the End?

Your response:

"I understand, and I appreciate that you plan to pay. Unfortunately, I can't front the entire project cost. Progress payments are how I ensure I can pay my crew and materials suppliers throughout the project. I'm happy to structure them in a way that makes sense for you, but I need to receive payment as work is completed."

If they still insist:

This is a red flag. Clients who won't agree to progress payments often don't plan to pay at the end either.

Handling Missed Progress Payments

What happens when a client doesn't make a progress payment?

  1. Stop work immediately. Don't continue past the milestone until payment is received.
  2. Send written notice. "Payment for milestone [X] was due on [date]. Work is paused until payment is received."
  3. Don't accept excuses. "I'll pay you next week" means you're now working for free.
  4. Resume only after payment. Don't restart until you have the check or confirmed transfer.

Critical: Your contract should include a stop work clause:

STOP WORK CLAUSE: If any progress payment is not received within [5] business days of the due date, Contractor shall have the right to stop work until payment is received. The project completion date shall be extended by the number of days work is stopped.

Progress Payments vs. Retainage

In some contracts, clients or GCs will hold back a percentage called retainage โ€” typically 5-10% โ€” until the project is complete.

Example:

Retainage is common in commercial work. For residential, you can often negotiate it down or eliminate it.

Tip: If retainage is required, negotiate a retainage cap. Instead of 10% on every payment, cap total retainage at 5% of the contract value. And specify when it's released โ€” 30 days after substantial completion, not "whenever the owner feels like it."

Key Takeaways

Progress payments aren't just about getting paid. They're about maintaining leverage throughout the project. When you have their money, they have to pay attention. When they have all your work, you have nothing.

Get the Complete System

Progress payments prevent problems. But when clients don't pay, you need a follow-up system. The Invoice Follow-Up Playbook includes templates for every stage โ€” from Day 1 reminders to demand letters. Combine good payment structure with good follow-up.

Get Quick Start โ€” $27 Get Full Playbook โ€” $47

Instant download. PDF + Markdown.